Metric Conversion Factors

Length Metric Conversion

1 Inch=25.4 Millimetre
1 Foot=0.3048 Metre
1 Yard=0.9144 metre
1 Mile=1.6093 Kilometer
1 Acre=0.4047 Hectare
1 Pound=0.4536 Kilogram
1 Millimetre=0.0394 Inch
1 Metre=3.2808 Foot
1 Metre=1.0936 Yard

Area Metric Conversion

1 ft2 =0.093 m2
1 yd2=0.836 m2
1 acre=0.405 ha (1 ha or hectare = 10000 m2)
1 mile2=2.590 m2
1 m2=10.764 ft2 = 1.196 yd2 (approximately 1.2 yd2)
1 ha =2.471 acres (approximately 2½ acres)
1 km2=0.386 mile2

Volume Metric Conversion

1 ft3 =0.028 m3
1 yd3=0.765 m3
1 m3=35.315 ft3 = 1.308 yd3 (approximately 1.3 yd3)
1 ft3 =28.32 litres (1000 litres=1 m3)
1 gal=4.546 litres
1 litre=0.220 gal (approximately 4½ litres to the gallon)

Mass Metric Conversion

1 lb=0.454 kg (kilogram)
1 cwt=50.80 kg (approximately 50 kg)
1 ton=1.016 tonnes (1 tonne= 1000 kg =0.984 ton)
1 kg=2.205 lb (approximately 2 1/5 lb)

The Weight of Steel for Different Bars Dia

6mm=0.222kg
8mm=0.395kg
10mm=0.616kg
12mm=0.888kg
16mm=1.578kg
20mm=2.466kg
25mm=3.853kg
32mm=6.313kg
40mm=9.865kg

Concrete Grade Materials Mix Ratio

M5=1:4:8
M10=1:3:6
M15=1:2:4
M20=1:1.5:3
M25=1:1:2

Clear Cover to Main Reinforcement

Footings: 50 mm
Raft Foundation Top: 50 mm
Raft Foundation Bottom/Sides: 75mm
Strap Beam: 50mm
Grade Slab:20mm
Column:40mm

9 Steps to Test Quality of Cement at Construction Site